Work Time : Rates Practice
This aptitude practice question is a Work Time problem solving question. Concept tested: The crux of solving this question entails framing proper equations from the information given in the word problem.
Question : Part 1
2. Framing equations for work time 2 concepts
Working together, A and B can do a job in 6 days. B and C can do the same job in 10 days, while C and A can do it in 7.5 days. How long will it take if all A, B, and C work together to complete the job?
- 8 days
- 5 days
- 3 days
- 7 days
Correct Answer Choice (2). If all 3 worked together, the will complete the job in 5 days.
Explanatory Answer
We know that if A and B work together, they can complete the job in 6 days. Therefore, if all three of them A, B and C work together the number of days it will take to complete the job will surely be less than 6 days. Hence, we can eliminate answer choices (1) and (4) right away.
Let A be the number of days that A will take to complete the job if A worked alone, B days for B to complete the job if B worked alone and C days for C to complete the job if C worked alone.
A and B can do a job in 6 days. They complete \\frac{1}{6}^{th}) of the job in a day.
i.e., \\frac{1}{A}) + \\frac{1}{B}) = \\frac{1}{6}) ------ (1)
Similarly, B and C will complete \\frac{1}{10}^{th}) of the job in a day.
i.e., \\frac{1}{B}) + \\frac{1}{C}) = \\frac{1}{10}) ------ (2)
And C and A will complete \\frac{1}{7.5}) or \\frac{2}{15}^{th}) of the job in a day
i.e., \\frac{1}{C}) + \\frac{1}{A}) = \\frac{2}{15}) ------ (3).
Adding (1), (2) and (3) we get \\frac{1}{A}) + \\frac{1}{B}) + \\frac{1}{B}) + \\frac{1}{C}) + \\frac{1}{C}) + \\frac{1}{A}) = \\frac{1}{6}) + \\frac{1}{10}) + \\frac{2}{15})
=> \\frac{2}{A}) + \\frac{2}{B}) = \\frac{2}{C}) = \\frac{5 + 3 + 4}{30}) = \\frac{12}{30})
Or \\frac{1}{A}) + \\frac{1}{B}) + \\frac{1}{C}) = \\frac{6}{30}) = \\frac{1}{5}).
i.e., working together, A, B and C complete 1/5th of the job in a day.
Therefore, they will complete the job in 5 days.
The correct answer is Choice (2).
Question Part 2
Working together, A and B can do a job in 6 days. B and C can do the same job in 10 days, while C and A can do it in 7.5 days. How long will A alone take to complete the job?
- 8 days
- 6 days
- 10 days
- 20 days
Correct Answer Choice (3). A alone will take 10 days
Explanatory Answer
From part 1, we know \\frac{1}{A}) + \\frac{1}{B}) + \\frac{1}{C}) = \\frac{1}{5}) .... (4)
From equation (2) in part 1, we know \\frac{1}{B}) + \\frac{1}{C}) = \\frac{1}{10})
Subtract (2) from (4): \\frac{1}{A}) + \\frac{1}{B}) + \\frac{1}{C}) - {\\frac{1}{B}) + \\frac{1}{C})} = \\frac{1}{5}) - \\frac{1}{10})
Or \\frac{1}{A}) = \\frac{2-1}{10}) = \\frac{1}{10})
If A completes \\frac{1}{10}) of the work in a day, A will take 10 days to complete the task if A worked alone.
The correct answer is Choice (3).
Online TANCET MBA Course
Try it Free!
Register in 2 easy steps and start learning in 5 minutes!
Already have an Account?
XAT TANCET Practice Questions - Listed Topic wise
- Number Theory
- Permutation Combination
- Probability
- Inequalities
- Geometry
- Coordinate Geometry
- Mensuration
- Trigonometry
- Data Sufficiency
- Percentages
- Profit Loss
- Ratio Proportion
- Mixtures & Alligation
- Speed Distance & Time
- Pipes, Cisterns & Work, Time
- Simple & Compound Interest
- Races
- Averages & Statistics
- Progressions : AP, GP & HP
- Set Theory
- Clocks Calendars
- Linear & Quadratic Equations
- Functions
- English Grammar
- General Awareness